NEPA PROCESS

This chart outlines the significant milestones in the National Environmental Policy Act (NEPA) process that the proposed marine container terminal at the Charleston Naval Complex (CNC) will go through. For your information the current status is noted below and will be updated as the process continues.  More information regarding the NEPA process is available here.

 

Notice of Intent (NOI) in Federal Register
Local Public Notice (PN)Distributed
Local Government Coordination
 
Public Agency Scoping Meetings
 
 
Selection of Reasonable Alternatives
 
 
Evaluation of Proposed Alternatives, Reasonable
Alternatives, and No-Action Alternatives
 
 
Distribution
Draft Environmental Impact Statements (DEIS)
 
 
Notice of Availability in the Federal Register
Notice to U.S. Environmental Protection Agency
 
 
Public and Agency Comment
 
 
Public Hearing
 
 
Public and Agency Comment
 
 
Corps Addresses Comments
 
 
Distribution
Final Environmental Impact Statements (FEIS)
 
 
Public and Agency Comment
 
 
Corps Issues Record of Decision (ROD)
 

 