Month/Year Milestone
Jan 2003 SCSPA Permit Application
Feb 2003 Determination of Environmental Impact Statement (EIS)
Mar 2003 US Army Corps of Engineers Public Notice
Apr 2003  
May 2003  
Jun 2003 Corps selects 3rd-Party Contractor, Applied Technology & Management, Inc. (ATM)
Jul 2003  
Aug 2003  
Sep 2003  
Oct 2003  
Nov 2003 SCSPA awards contract to ATM
Dec 2003 Preparation for "Scoping"
Jan 2004 ""  ""
Feb 2004 ""  ""
Mar 2004 Public and Agency Scoping Meetings  more info
Apr 2004 Corps Develops Scope of Work
May 2004 ""  ""
Jun 2004 ""  ""
Jul 2004 ""  ""
Aug 2004 ""  ""
Sep 2004 ""  ""
Oct 2004 ""  ""
Nov 2004 ""  ""
Dec 2004 ""  ""
Jan 2005 Scope of Work Authorized, Preparation of Draft EIS
Feb 2005 Preparation of Draft EIS
Mar 2005 ""  ""
Apr 2005 ""  ""
May 2005 ""  ""
Jun 2005 ""  ""
Jul 2005 ""  ""
Aug 2005 ""  ""
Sep 2005 ""  ""
Oct 2005 Publication of Draft EIS
Nov 2005 Public Hearing and Comment Period
Dec 2005 ""  ""
Jan 2006 Preparation of Final EIS
Feb 2006 ""  ""
Mar 2006 ""  ""
Apr 2006 ""  ""
May 2006 ""  ""
Jun 2006 ""  ""
Jul 2006 ""  ""
Aug 2006 ""  ""
Sep 2006 ""  ""
Oct 2006 ""  ""
Nov 2006 ""  ""
Dec 2006 Publication of Final EIS
Jan 2007 ""  ""
Feb 2007 Record of Decision
Mar 2007 ""  ""
Schedule Last Updated: January 20, 2005